Midwater continues to progress nicely through each level’s slab pour, level 32 has been poured recently. Level 33 is formed ready for reinforcing.
Glazing & Internal Fit-out: – The glazing installation has been completed on level 26, with level 11 having been completed for internal partition walls.
Final Basement Level: – Below the ground, basement structural works are nearing completion. B7 has recently been poured.
Additional News: – The lift core has now progressed to level 37. All doors up to level 12 have been installed.
Estimated Completion Date: Early to mid-2025